Preliminary Lien Notice Deadlines by State
Get Texas, California, Michigan and Georgia statutory lien waivers filled in free, no account. State Lien Kits from $49 for 12 months.
Get the free waiversMost states make subcontractors and suppliers send an early notice to keep their lien rights: 20 days in California, Arizona and Michigan, 21 days in Ohio (only when a notice of commencement is recorded), 30 days in Georgia (only when a notice of commencement is filed), and in Texas the 15th day of the 3rd month after each unpaid month (the 2nd month on residential jobs). Miss it and the lien you file later can fail, however much you are owed.
The deadlines, state by state
| State | Notice | Deadline | Delivery that counts | Law |
|---|---|---|---|---|
| California | 20-day preliminary notice, to the owner, direct contractor and construction lender | 20 days after first furnishing; a late notice covers only the 20 days before it and later work | Personal delivery, registered, certified or express mail, or overnight carrier; not plain first-class mail | Civ. Code 8200 to 8216, 8110 |
| Arizona | Preliminary twenty-day lien notice | 20 days after first furnishing; a late notice covers only the 20 days before it | First-class mail with a certificate of mailing, or registered or certified mail | A.R.S. 33-992.01 |
| Michigan | Notice of furnishing, to the designee and the general contractor | 20 days after first furnishing (laborers: 30 days after wages are due) | Personally or by certified mail; complete on mailing | MCL 570.1109 |
| Ohio | Notice of furnishing, to the owner's designee | 21 days after first furnishing, only if the owner recorded a notice of commencement; never on home construction contracts; a late notice covers only the 21 days before it | Certified or registered mail, overnight delivery, hand delivery or any method with written proof of receipt | R.C. 1311.05, 1311.19 |
| Georgia | Notice to contractor, to the owner and the contractor | 30 days after the later of the notice of commencement filing or your first delivery; only if a notice of commencement was filed | Registered or certified mail, or statutory overnight delivery | O.C.G.A. 44-14-361.5 |
| Texas | Notice of claim for unpaid labor or materials, to the owner and the original contractor | 15th day of the 3rd month after each month you furnished and were not paid (2nd month on residential jobs); retainage has its own notice | In person, certified mail, or a traceable carrier that confirms receipt; not first-class mail with a certificate | Prop. Code 53.056, 53.057, 53.003 |
| Iowa | Residential: preliminary notice posted on the state registry (MNLR). Commercial: sub-subcontractor notice to the general contractor | Residential: no day count, but what you can recover is capped by what the owner still owes when notified. Commercial: 30 days after first furnishing | MNLR posting (the state mails the owner); commercial notice in writing | Iowa Code 572.13B, 572.33 |
| Florida | Notice to Owner | Before you start or within 45 days of first furnishing | Certified, registered or Global Express Guaranteed mail (713.18) | Fla. Stat. 713.06; see FloridaNTO |
Weekends and holidays
California, Texas, Georgia, Michigan and Florida move a deadline that falls on a weekend or legal holiday to the next business day (Code Civ. Proc. 12a; Tex. Prop. Code 53.003(e); O.C.G.A. 1-3-1(d)(3); MCL 8.6; Fla. Stat. 713.011). Ohio and Arizona do not move a Saturday deadline (R.C. 1.14; A.R.S. 1-243), and for Iowa registry postings only a Sunday moves (Iowa Code 4.1(34)). If in doubt, send it a day early. Our lien deadline calculator applies each state's own rule and holiday list.
Three rules that catch people
- Some notices exist only after a notice of commencement. In Georgia and Ohio the early notice is required only when the owner filed or recorded one, so check the county records, or ask the owner, before you decide you need nothing.
- Late is better than never in California, Arizona and Ohio: a late notice still protects the most recent 20 or 21 days and everything after.
- Texas counts months, not days, and each unpaid month starts its own clock. A job with three unpaid months can need three notices.
Keep proof
Whatever the state, keep the mailing receipt, tracking record or signed delivery receipt for every notice. California asks for a signed proof of notice declaration with the USPS or carrier record (Civ. Code 8118), and Michigan requires proof of notice of furnishing service to be attached to a claim of lien (MCL 570.1111). Our kits include a proof-of-mailing log with each state's delivery rules.
State guides and tools
California 20-day preliminary notice · Texas notice of claim and deadlines · Georgia notice to contractor · Michigan notice of furnishing · Ohio notice of furnishing · Iowa MNLR · Arizona deadlines · Florida Notice to Owner. The State Lien Kit ($49 per state, 12 months) fills in the Texas, Georgia, Michigan, Ohio and Iowa notices from the facts you type.
Last reviewed November 22, 2026, from the statutes cited above (state library checked November 21, 2026). Forms software, not a law firm; not a substitute for the advice of an attorney.