Ohio is the state where a Saturday deadline does not move. It also turns its notice rules off completely on home construction contracts. Get these two points right and the rest is straightforward.

Notice of commencement

The owner records a notice of commencement with the county recorder before work starts and keeps a copy posted on the site (R.C. 1311.04, as amended effective September 30, 2025). It expires 4 years after recording unless it states another date. It does not apply to home construction contracts. Every required item, posting and copies: Ohio notice of commencement.

Notice of furnishing: 21 days

Only when a notice of commencement was recorded, a subcontractor or supplier serves a notice of furnishing on the owner's designee and the original contractor within 21 days after first furnishing (1311.05). Certified mail is served on the mailing date (1311.19). A late notice protects only what you furnished in the 21 days before you served it, and after. No notice of furnishing applies on home construction contracts (1311.05(E)). If you contract directly with the original contractor, you serve only the designee, not that contractor.

Late or missing notice of commencement

If the owner records the notice of commencement after you started, your 21 days run from the day it was recorded (1311.04(I)). If you do not have it, ask for a copy in writing by certified mail: the owner, part owner, lessee or designee must serve a copy within ten days after your request (1311.04(D)). If they do not, your notice of furnishing deadline is extended until 21 days after the copy is actually served on you, and the owner is liable for your costs of getting the information (1311.04(J)). Example: first furnishing November 2, 2026, notice of commencement recorded November 10, 2026: notice of furnishing by Tuesday, December 1, 2026.

Lien affidavit

Record the affidavit for mechanic's lien with the county recorder within 75 days after your last work, 60 days for a one- or two-family dwelling or residential condo unit, and 120 days for oil and gas well work (1311.06). It is sworn. Serve a copy on the owner or designee within 30 days after recording, or post it on the property within 10 more days (1311.07). The lien lasts 6 years (1311.13), but if the owner serves a notice to commence suit you must sue within 60 days (1311.11).

Home construction: speed matters

On a home construction contract, if the owner pays the original contractor in full before receiving a copy of your lien affidavit, subcontractor liens are lost (1311.011). Record and serve quickly.

Saturdays

Ohio moves a deadline only when the last day is a Sunday or legal holiday (R.C. 1.14). A notice due on a Saturday is due that Saturday. An act that must be done at a public office closed that Saturday, like recording, may be done on the next day that is not a Sunday or holiday. Example: first furnishing November 2, 2026 with a recorded notice of commencement: notice of furnishing by Monday, November 23, 2026 (day 21 is a Monday).

Waivers

Ohio has no statutory waiver form; releases are drafted freely, and the person paying you may require its own form. Prefer a conditional release until the money clears, and list every amount you are not giving up. We do not prepare, file or record lien affidavits for others in Ohio (Ohio State Bar Assn. v. Lienguard, 2010).

The Ohio Lien Kit

Our Ohio kit fills in the 1311.05(B) notice of furnishing (with a sending record that shows your serve-by date under Ohio's Saturday rule), a certified-mail request for a copy of the notice of commencement, the owner's notice of commencement affidavit with every 1311.04(B) item and a 3-inch top margin for the recorder, plain non-statutory progress and final waivers, and a proof-of-mailing log. You type the facts, sign and send.

Related: preliminary notice deadlines by state · how to file a mechanics lien · weekend and holiday rules · lien deadline calculator · Ohio Lien Kit, $49

Read November 21, 2026. General information, not legal advice, and not a substitute for the advice of an attorney.