Lien Waiver vs Lien Release: What's the Difference? (2026)
Short answer: a lien waiver is signed when you are paid and gives up your right to file a lien for that payment; it is usually handed to the payer, not recorded. A lien release (called a release, cancellation, discharge or satisfaction depending on the state) removes a lien that has already been recorded. The lien claimant signs it after being paid, and it is recorded where the lien was recorded.
Waiver or release?
| Lien waiver | Lien release | |
|---|---|---|
| When | At each payment, usually before any lien is filed | After a lien has been recorded and then paid, bonded or resolved |
| What it does | Gives up the right to claim a lien for the amount paid | Clears the recorded lien from the property records |
| Who signs | The sub, supplier or contractor being paid | The lien claimant |
| Recorded? | Usually not | Yes, in the same office as the lien |
| State forms | Statutory forms in some states (Texas, Arizona, Michigan, Georgia, Florida models) | No statutory release form in the states below; the recording office's own requirements apply |
Releasing a recorded lien in our kit states
| State | What the law says | Where |
|---|---|---|
| Texas | Once the debt is paid by collected funds, the claimant must furnish a release “not later than the 10th day after the date of receipt of a written request”; the owner, original contractor or payer may request it, and it must be in a form that can be filed of record (Prop. Code 53.152). Recording a release signed by the claimant discharges the lien of record (53.157(1)). | County clerk where the lien affidavit was filed |
| Georgia | Liens are filed with the clerk of superior court of the county where the property is. Cobb County's clerk form, for example, has the lien claimant sign a cancellation under the original lien, and the clerk satisfies it of record. Check your county clerk's steps and fee. | Clerk of superior court of the county |
| Michigan | A claimant paid in full must give the owner, lessee or designee a full unconditional waiver (MCL 570.1115(2)). A claim of lien may also be discharged by filing a bond for twice the amount claimed with the county clerk (570.1116). | Claims of lien are recorded with the register of deeds; bonds go to the county clerk |
| Ohio | A lienholder who fails “within thirty days” after the lien is satisfied or adjudged “to cause the lien to be released” is liable to the owner for damages up to the lien amount and costs (R.C. 1311.20). On a home construction contract, a lienholder who does not cause the lien to be released of record within 30 days after the owner's written notice that the original contractor was paid in full before the owner received a copy of the lien affidavit is liable for damages (1311.011(B)(3)). | County recorder (the recorder may require a separate acknowledged release) |
| Iowa | A claimant whose lien is paid must acknowledge satisfaction. If it does not within 30 days after a written demand is personally served, it forfeits $25 to the owner, general contractor or owner-builder and is liable for any injury caused, and the person who served the demand may file a copy of it, with proof of service, with the registry administrator, which gives notice of the forfeiture and cancellation of the lien (Iowa Code 572.23). | Iowa Secretary of State's MNLR |
What we do and do not prepare
Lien Rights Kit prepares preliminary notices and lien waiver forms from the facts you type. We do not prepare lien releases, cancellations, satisfactions or lien affidavits. To release a lien, use your recording office's own process (links below) or ask an attorney.
Waivers, free
Fill in the statutory waiver forms free: Texas, Michigan and Georgia; Florida's forms come blank. Related: partial vs final lien waivers · subcontractor lien waivers · how to file a mechanics lien.
Sources
- Texas Property Code chapter 53 (53.152, 53.157)
- Cobb County Clerk of Superior Court: lien form with cancellation
- MCL 570.1115
- MCL 570.1116
- R.C. 1311.20
- R.C. 1311.011
- Iowa Code 572.23
- Iowa Mechanics' Notice and Lien Registry (MNLR)
Statutes read on November 23, 2026. General information, not legal advice, and not a substitute for the advice of an attorney. Lien Rights Kit is forms software, not a law firm.
- Texas Property Code chapter 53 (53.152, 53.157) (statutes.capitol.texas.gov)
- MCL 570.1115 (legislature.mi.gov)
- MCL 570.1116 (legislature.mi.gov)
- R.C. 1311.20 (codes.ohio.gov)
- R.C. 1311.011 (codes.ohio.gov)
- Iowa Code 572.23 (legis.iowa.gov)
- Iowa Mechanics' Notice and Lien Registry (MNLR) (sos.iowa.gov)
Sources: statutes.capitol.texas.gov, legislature.mi.gov, codes.ohio.gov · 3 min read
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing