Short answer: a lien waiver is signed when you are paid and gives up your right to file a lien for that payment; it is usually handed to the payer, not recorded. A lien release (called a release, cancellation, discharge or satisfaction depending on the state) removes a lien that has already been recorded. The lien claimant signs it after being paid, and it is recorded where the lien was recorded.

Lien waiver forms by state

Waiver or release?

Lien waiverLien release
WhenAt each payment, usually before any lien is filedAfter a lien has been recorded and then paid, bonded or resolved
What it doesGives up the right to claim a lien for the amount paidClears the recorded lien from the property records
Who signsThe sub, supplier or contractor being paidThe lien claimant
Recorded?Usually notYes, in the same office as the lien
State formsStatutory forms in some states (Texas, Arizona, Michigan, Georgia, Florida models)No statutory release form in the states below; the recording office's own requirements apply

Releasing a recorded lien in our kit states

StateWhat the law saysWhere
TexasOnce the debt is paid by collected funds, the claimant must furnish a release “not later than the 10th day after the date of receipt of a written request”; the owner, original contractor or payer may request it, and it must be in a form that can be filed of record (Prop. Code 53.152). Recording a release signed by the claimant discharges the lien of record (53.157(1)).County clerk where the lien affidavit was filed
GeorgiaLiens are filed with the clerk of superior court of the county where the property is. Cobb County's clerk form, for example, has the lien claimant sign a cancellation under the original lien, and the clerk satisfies it of record. Check your county clerk's steps and fee.Clerk of superior court of the county
MichiganA claimant paid in full must give the owner, lessee or designee a full unconditional waiver (MCL 570.1115(2)). A claim of lien may also be discharged by filing a bond for twice the amount claimed with the county clerk (570.1116).Claims of lien are recorded with the register of deeds; bonds go to the county clerk
OhioA lienholder who fails “within thirty days” after the lien is satisfied or adjudged “to cause the lien to be released” is liable to the owner for damages up to the lien amount and costs (R.C. 1311.20). On a home construction contract, a lienholder who does not cause the lien to be released of record within 30 days after the owner's written notice that the original contractor was paid in full before the owner received a copy of the lien affidavit is liable for damages (1311.011(B)(3)).County recorder (the recorder may require a separate acknowledged release)
IowaA claimant whose lien is paid must acknowledge satisfaction. If it does not within 30 days after a written demand is personally served, it forfeits $25 to the owner, general contractor or owner-builder and is liable for any injury caused, and the person who served the demand may file a copy of it, with proof of service, with the registry administrator, which gives notice of the forfeiture and cancellation of the lien (Iowa Code 572.23).Iowa Secretary of State's MNLR

What we do and do not prepare

Lien Rights Kit prepares preliminary notices and lien waiver forms from the facts you type. We do not prepare lien releases, cancellations, satisfactions or lien affidavits. To release a lien, use your recording office's own process (links below) or ask an attorney.

Waivers, free

Fill in the statutory waiver forms free: Texas, Michigan and Georgia; Florida's forms come blank. Related: partial vs final lien waivers · subcontractor lien waivers · how to file a mechanics lien.

Sources

Statutes read on November 23, 2026. General information, not legal advice, and not a substitute for the advice of an attorney. Lien Rights Kit is forms software, not a law firm.

Sources cited in this guide

Sources: statutes.capitol.texas.gov, legislature.mi.gov, codes.ohio.gov · 3 min read

Lien Rights Kit
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing

Also from our guides