Get the free waiversSince January 1, 2022, when House Bill 2237 took effect, a Texas subcontractor or supplier on a private project protects lien rights for unpaid work with one notice: the notice of claim for unpaid labor or materials in Texas Property Code § 53.056. It replaced the older second-month and third-month notices and the separate residential notice.
Who must send it
Every claimant other than an original contractor must give the notice for the lien to be valid (§ 53.056(a)). An original contractor is the one with a direct contract with the owner; subcontractors, sub-subcontractors and suppliers are the ones who send this notice. A claim for unpaid retainage has its own notice under § 53.057.
The deadline
For all unpaid labor or materials, send the notice not later than the 15th day of the third month after the month during which you provided them. On a residential construction project, the deadline is the 15th day of the second month (§ 53.056(a-1)). For specially fabricated materials that were not delivered, count from the month they would normally have been delivered.
If the last day is a Saturday, Sunday or legal holiday, the period runs to the next day that is not a Saturday, Sunday or legal holiday (§ 53.003(e)). Each unpaid month has its own deadline.
| Month provided | Commercial or other project | Residential project |
|---|---|---|
| September 2026 | Tuesday, December 15, 2026 | Monday, November 16, 2026 |
| October 2026 | Friday, January 15, 2027 | Tuesday, December 15, 2026 |
| November 2026 | Tuesday, February 16, 2027 | Friday, January 15, 2027 |
| December 2026 | Monday, March 15, 2027 | Tuesday, February 16, 2027 |
| January 2027 | Thursday, April 15, 2027 | Monday, March 15, 2027 |
| February 2027 | Monday, May 17, 2027 | Thursday, April 15, 2027 |
| March 2027 | Tuesday, June 15, 2027 | Monday, May 17, 2027 |
November 15, 2026 is a Sunday, February 15, 2027 is Presidents’ Day and May 15, 2027 is a Saturday, so those deadlines move to the next business day. Do not plan on the extra day: send early. Check a month with the free deadline check.
What the notice must say
The statute sets the form (§ 53.056(a-2)). The notice must be in substantially this form: the date; the project description and/or address; the claimant’s name; the type of labor or materials provided; the original contractor’s name; the party the claimant contracted with, if different from the original contractor; the claim amount; the claimant’s contact person; and the claimant’s address. You may include an invoice or billing statement (§ 53.056(a-3)).
Who receives it, and how
Send it to the owner or reputed owner and to the original contractor (§ 53.056(a-1)). Deliver it in person, by certified mail, or by any other form of traceable, private delivery or mailing service that can confirm proof of receipt (§ 53.003(b)). If you use certified mail, depositing the notice in the U.S. mail in the required form is compliance (§ 53.003(c)). Keep the receipts with your job file.
Residential or not?
The shorter deadline applies to residential construction projects. The Property Code ties that term to residences such as a single-family house, duplex, triplex or quadruplex, and certain owner-occupied units (§ 53.001). If you are not sure which deadline applies, use the earlier one.
What comes next
The notice keeps your lien claim possible; it is not the lien itself. The lien affidavit has its own filing deadline (§ 53.052; see Texas mechanics lien deadlines), and retainage has its own notice (§ 53.057).
Lien Rights Kit fills in the § 53.056(a-2) form from your job details and works out the send-by date for the month you enter (one notice per unpaid month), with a sending record page for certified mail. See plans.
Sources: Texas Property Code §§ 53.003 and 53.056, statute text as amended by H.B. 2237 (87th Legislature), effective January 1, 2022, read 21 November 2026. General information, not legal advice.