Georgia ties one preliminary notice to the notice of commencement. When an owner or contractor files a notice of commencement, a subcontractor or supplier who has no contract with the contractor must send a notice to contractor to keep the lien rights covered by O.C.G.A. 44-14-361.5.

When it applies

It applies to a person with a right to a lien who does not have privity of contract with the contractor and is providing labor, services or materials, on a project for which a notice of commencement has been filed with the clerk of the superior court (44-14-361.5(a)). If no notice of commencement was filed, the section does not apply (44-14-361.5(d)).

The notice of commencement

It must be filed not later than 15 days after the contractor physically starts work, by the owner, the owner’s agent or the contractor, with the clerk of the superior court in the county of the project, and posted on the project site (44-14-361.5(b)). It lists the contractor, the project and legal description, the true owner, the person at whose instance the work is done if not the owner, the surety, and the construction lender.

The contractor must give a copy to any subcontractor, materialman or person who asks in writing. If the contractor does not give it within ten calendar days of the written request, the section does not apply to the person who asked (44-14-361.5(b)).

The 30-day deadline

Send the notice to contractor within 30 days from the filing of the notice of commencement or 30 days following your first delivery of labor, services or materials to the property, whichever is later (44-14-361.5(a)). Example: the notice of commencement was filed on November 2, 2026 and your first delivery was November 10, 2026; count 30 days from November 10, which gives December 10, 2026.

What to include

  1. Your name, address and telephone number.
  2. The name and address of each person at whose instance the labor, services or materials are being furnished.
  3. The name and location of the project as set forth in the notice of commencement.
  4. A description of the labor, services or materials and, if known, the contract price or anticipated value, or the amount claimed to be due.

The statute lists these items (44-14-361.5(c)); it does not give fixed wording.

How to send it

By registered or certified mail or statutory overnight delivery, to the owner or the owner’s agent and to the contractor, at the addresses set forth in the notice of commencement (44-14-361.5(c)). Keep the receipts.

Related Georgia rules

Georgia lien waivers must use the statutory forms in O.C.G.A. 44-14-366. See Georgia lien waivers and the 90-day rule.

Lien Rights Kit fills in the notice to contractor with every item the statute lists and works out the 30-day date from the later of your two dates, with a sending record page. See plans.

Sources: O.C.G.A. 44-14-361.5 (2025 Georgia Code, law.justia.com), read 21 November 2026. General information, not legal advice.

2 min read

Lien Rights Kit
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing

Also from our guides