Ohio Notice of Commencement (2026): Who Records It and What It Says

Short answer: in Ohio the owner, part owner or lessee who contracts for the work records a notice of commencement with the county recorder before any labor or materials are furnished, and keeps a copy posted on the job site (R.C. 1311.04). It expires four years after recording unless it states another date. Subcontractors and suppliers use it to serve their 21-day notice of furnishing. It does not apply to a home construction contract unless a lender requires one.

Ohio Lien Kit: owner's notice of commencement, notice of furnishing and request letter ($49)

Who records it, when and where

R.C. 1311.04(A)(1): “Prior to the performance of any labor or work or the furnishing of any materials for an improvement on real property”, the owner, part owner or lessee who contracts for the work records the notice “in the office of the county recorder for each county in which the real property to be improved is located”, in substantially the form in division (B). One notice covers one improvement; later notices for the same improvement count as amendments, and an added original contractor, lender or surety needs an amended notice (1311.04(A)(2)). The statute sets no dollar threshold.

What it must contain

The notice is in affidavit form and lists (1311.04(B)):

  1. The legal description of the property
  2. A brief description of the improvement
  3. The name, address and capacity of the owner, part owner or lessee who contracted
  4. The fee owner, if the contracting party is a land contract vendee or a lessee
  5. The owner's designee, if any
  6. Every original contractor (on a single- or double-family dwelling with several, the owner may state that “multiple original contractors are involved”)
  7. The date the owner first signed a contract with an original contractor
  8. Any lending institution
  9. Any surety on a bond
  10. The statutory notice to lien claimants, which begins “To Lien Claimants and Subsequent Purchasers: Take notice that labor or work is about to begin…”
  11. The name and address of the person who prepared it
  12. “The expiration date for this notice of commencement is four years from the date of recording unless a different date is specified herein.”
  13. The owner's or agent's verification

Posting and copies

  • Post it: the owner or designee “shall post and maintain posted a copy of the notice of commencement in a conspicuous place on the real property” during the physical work (1311.04(G)(1)).
  • Give it to the original contractor (1311.04(H)).
  • Copies on request: within ten days after a subcontractor, supplier or laborer serves a written request, the owner or designee must serve a copy (1311.04(D)); original contractors and subcontractors must answer requests too (1311.04(E), (F)). The statutory notice itself says a copy may be obtained by written request by certified mail.

If the owner does not record, post or answer

  • No notice recorded: a subcontractor's or supplier's notice of furnishing deadline is extended until 21 days after it is recorded (1311.04(I)).
  • No copy served on request: the deadline is extended until 21 days after a copy is actually served, and the owner is liable for the claimant's actual expenses of getting the information (1311.04(J)); the same expenses apply when the notice is not posted (1311.04(K)).
  • Wrong information: the owner is liable for any loss of lien rights and actual expenses, including attorney's fees, that result directly from the claimant's reliance on it (1311.04(C)).
  • The original contractor may record the notice itself after the later of ten days after work starts or three days after it serves a demand to record (1311.04(N)); a mortgage holder may also record it.

Ending it

When the improvement is complete, the owner or its agent may submit to the county recorder an affidavit stating that the improvement is complete (often called an affidavit of completion); the recorder then marks the notice of commencement expired, and the owner mails a copy to the original contractor and to each subcontractor who served a notice of furnishing (1311.04(T)). Expiration does not affect “the attachment, continuance, or priority of any lien” (1311.04(U)).

Homes: the notice usually does not apply

Section 1311.04 “does not apply to a home construction contract as defined in section 1311.011”: a contract to improve a single- or double-family dwelling or condominium unit used or intended as a personal residence. If a lender requires a notice of commencement for a mortgage-financed home construction contract, the owner may record one, but the notice of furnishing rules still do not apply (1311.04(O); 1311.05(E)). On a home, an owner who pays the original contractor in full before receiving a copy of a lien affidavit is protected from subcontractor liens (1311.011(B)(1)).

How subs and suppliers use it

When a notice of commencement is recorded, a subcontractor or supplier who wants to keep lien rights serves a notice of furnishing on the owner's designee (or the owner) and on the original contractor “within twenty-one days after performing the first labor or work or furnishing the first materials” (1311.05). A late notice protects only work and materials from the 21 days before it was served, and after. Lien affidavits are recorded with the county recorder within 60 days for a one- or two-family dwelling or residential condo unit and 75 days for most other work (1311.06). Full deadlines and Ohio's Saturday rule: Ohio mechanics lien deadlines.

The Ohio Lien Kit

Our Ohio kit fills in the owner's notice of commencement affidavit with every 1311.04(B) item and a 3-inch top margin for the recorder, the 1311.05(B) notice of furnishing with your serve-by date, a certified-mail request for a copy of the notice of commencement, plain non-statutory progress and final waivers, and a proof-of-mailing log. You type the facts, sign, record and send. $49 for 12 months: see the kit. Free first: the lien deadline calculator.

Related: Ohio mechanics lien deadlines · preliminary notice deadlines by state · lien waiver vs lien release

Sources

Statutes read on November 23, 2026. General information, not legal advice, and not a substitute for the advice of an attorney. Lien Rights Kit is forms software, not a law firm.

Sources: codes.ohio.gov · 5 min read

Lien Rights Kit
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing

Also from our guides