Michigan's Construction Lien Act asks subcontractors and suppliers for one notice early and one lien at the end, and it is strict about paperwork: the register of deeds rejects documents that do not meet its format rules.

Notice of commencement

On non-residential jobs the owner or lessee records a notice of commencement with the register of deeds before work begins and posts it on the site (MCL 570.1108). For residential structures the owner must provide one within 10 days of a written request sent by certified mail (570.1108a). It names the designee who receives your notices.

Collecting lien waivers from your subs? Send each sub one free link. They fill in their own part of the state form, sign it and email it back to you.

Michigan

You pick the state form and type the project facts; each sub types its own facts and signs. Nothing is stored or sent by Lien Rights Kit. Forms software, not a law firm.

Notice of furnishing: 20 days

If you are a subcontractor, supplier or laborer, serve a notice of furnishing on the designee and the general contractor named in the notice of commencement within 20 days after you first furnish, personally or by certified mail; service by certified mail is complete on mailing (570.1109). A late notice does not forfeit the lien, but the lien is reduced by what the owner paid before receiving it. Keep the proof of mailing: a claim of lien must attach it (570.1111(4)).

Claim of lien: 90 days

Record the claim of lien with the register of deeds within 90 days after your last furnishing (570.1111(1)). It is sworn before a notary. Within 15 days after recording, serve it, with the notice-of-furnishing proof, on the designee by certified mail, return receipt requested (570.1111(5)). Foreclose within 1 year after recording and record a lis pendens (570.1117). The register may not record a document that misses its format rules, including a 2.5-inch top margin, 10-point type and the drafter's name and address (565.201).

Example

First furnishing November 2, 2026: notice of furnishing by Monday, November 23, 2026 (day 20 is a Sunday). Last furnishing January 8, 2027: claim of lien by Thursday, April 8, 2027.

Waivers and homeowners

Michigan prescribes four waivers: partial and full, conditional and unconditional (570.1115(9)). No notary is needed. A claimant who receives full payment must give a full unconditional waiver (570.1115(2)). Fill them in free with our Michigan lien waiver forms. The Homeowner Construction Lien Recovery Fund was abolished in 2010; older forms that mention it are out of date.

Weekends and holidays

A last day on a Saturday, Sunday or legal holiday moves to the next day that is none of these (MCL 8.6). Michigan's legal holidays include February 12 and June 19 (435.101).

Related: conditional lien waivers · unconditional lien waivers · preliminary notice deadlines by state · lien deadline calculator · Michigan Lien Kit, $49

Read November 21, 2026. General information, not legal advice, and not a substitute for the advice of an attorney.

Published November 21, 2026 · 2 min read

Lien Rights Kit
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing

Also from our guides