Iowa does not record liens at the county. Every commencement notice, preliminary notice and lien is posted on the Secretary of State's Mechanics' Notice and Lien Registry (MNLR), and the state mails the owner. The fees are low: about $7 to post a notice and $30 for a lien online. What costs money in Iowa is posting late.

Commencement notice: 10 days

On a one- or two-family dwelling, a general contractor or owner-builder that uses subcontractors posts a commencement notice on the MNLR no later than 10 days after work starts (Iowa Code 572.13A). A general contractor that fails to post it has no lien. It must also give the owner the bold statutory notice in 572.13.

Preliminary notice (residential)

Residential subcontractors post a preliminary notice on the MNLR. There is no fixed day count, but your lien is limited to what the owner still owes the general contractor when the owner receives your notice (572.13B), so post it at the start of the job.

Commercial: 30-day notice

On commercial jobs, if you furnish to a subcontractor, give written notice to the general contractor within 30 days of first furnishing (572.33), by a method that proves receipt.

The lien: 90 days, then limited

Post the lien within 90 days after your last furnishing for full rights (572.9). After that a lien can still be posted up to 2 years and 90 days after last furnishing, but you must serve the owner like a court original notice and recovery is limited to what the owner still owes (572.10, 572.11). The lawsuit deadline runs 2 years from the end of the 90 days, or 30 days after an owner's demand to sue (572.27, 572.28).

Sundays only

For registry postings, only a Sunday deadline moves to Monday; Saturdays and holidays do not (4.1(34)). Example: last furnishing January 8, 2027: post the lien by Thursday, April 8, 2027.

Waivers

Iowa has no statutory waiver form. Commercial owners may require waivers from everyone who furnished before paying early (572.33A).

Related: preliminary notice deadlines by state · how to file a mechanics lien · lien deadline calculator · Iowa Lien Kit, $49

Read November 21, 2026. General information, not legal advice, and not a substitute for the advice of an attorney.