Arizona Mechanics Lien Deadlines: 20-Day Notice, 120 Days

Get Texas, California, Michigan and Georgia statutory lien waivers filled in free, no account. State Lien Kits from $49 for 12 months.

Get the free waivers

In Arizona even the original contractor sends a preliminary notice, the lien must attach that notice, and the lien dies after six months unless you sue. Saturdays do not extend deadlines.

Preliminary twenty day notice

Everyone who furnishes labor, professional services, materials, machinery, fixtures or tools, except wage laborers, serves a preliminary twenty day notice within 20 days after first furnishing on the owner, the original contractor, the construction lender and the person who hired them (A.R.S. 33-992.01(B), (C)). First-class mail with a certificate of mailing, or certified or registered mail, is allowed; service is complete on deposit (33-992.01(F)). A late notice covers what you furnished from 20 days before it is served (33-992.01(E)). If the estimated price rises 30% or more, send a new notice (33-992.01(G)).

Recording the lien

Record the notice and claim of lien with the county recorder within 120 days after completion, or 60 days after the owner records a notice of completion that was mailed to you (33-993). It is made under oath and must attach a copy of your preliminary notice and its proof of mailing. Serve a copy on the owner within a reasonable time.

The 6-month lapse

The lien lapses 6 months after recording unless you file a foreclosure action and record a lis pendens within that time (33-998).

Owner-occupied homes

No lien may be recorded against an owner-occupant's dwelling unless the claimant has a written contract directly with the owner-occupant (33-1002). Subcontractors and suppliers on those homes have no lien.

Saturdays and holidays

A deadline on a Sunday or holiday moves to the next business day; Saturday is not a holiday in Arizona (1-243, 1-301, 1-303). Example: completion December 18, 2026 gives day 120 on Saturday, April 17, 2027; record by Friday, April 16, because recorders are closed on Saturday.

Waivers

Arizona prescribes four waiver forms in 33-1008: conditional and unconditional, progress and final. A waiver is effective only if it follows the statutory form substantially and is signed. Our Arizona forms are in review for Arizona's legal document preparer rules and are not offered yet; use the deadline calculator for Arizona dates.

Read November 21, 2026. General information, not legal advice, and not a substitute for the advice of an attorney.