California gives every subcontractor and supplier two hard steps: a 20-day preliminary notice at the start, and a lien recorded inside a window that closes 90 days after the project is complete, or sooner if the owner records a notice of completion. Miss either and the lien is gone.

20-day preliminary notice

Serve it within 20 days after you first furnish work on the job, on the owner or reputed owner, the direct contractor and the construction lender, if any (Civ. Code 8200, 8204). A direct contractor sends it only to the lender. It must carry the information in 8102 and 8202 and the boldface NOTICE TO PROPERTY OWNER. Serve it by personal delivery or by registered, certified or express mail or overnight delivery; plain first-class mail is not enough (8106, 8110). A late notice still works, but it covers only what you furnished in the 20 days before you served it, and after (8204(a)). Full details: California 20-day preliminary notice guide.

Collecting lien waivers from your subs? Send each sub one free link. They fill in their own part of the state form, sign it and email it back to you.

California

You pick the state form and type the project facts; each sub types its own facts and signs. Nothing is stored or sent by Lien Rights Kit. Forms software, not a law firm.

Recording the mechanics lien

  • A subcontractor or supplier records after it stops furnishing and before the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation (8414).
  • A direct contractor records after completing its contract and before the earlier of 90 days after completion or 60 days after a recorded notice of completion or cessation (8412).
  • The shorter window applies only if the notice of completion was recorded within 15 days after completion and the owner mailed you a copy within 10 days after recording (8182, 8190).

Recording too early is as fatal as recording too late.

Serve before you record

The lien must include a proof of service affidavit showing that a copy was served on the owner by registered, certified or first-class mail with a certificate of mailing (8416(a)(7), (c)). Without it the lien is unenforceable (8416(e)). It must also include the 10-point bold NOTICE OF MECHANICS LIEN (8416(a)(8)). The claim is verified; no notary is needed (8416(b)). Recorders charge the $75 SB2 fee on mechanics liens (Gov. Code 27388.1).

Foreclosure

File the foreclosure action within 90 days after recording, or the lien expires (8460), and record a lis pendens within 20 days after filing (8461).

Example

First day on the job November 2, 2026: preliminary notice by Monday, November 23, 2026 (day 20 is a Sunday). Project complete December 18, 2026 with no notice of completion: record by Thursday, March 18, 2027.

Weekends, holidays and waivers

California extends a deadline that falls on a Saturday, a Sunday or a judicial holiday to the next day that is not one (Code Civ. Proc. 12a, 135), including the day after Thanksgiving. Waivers must substantially follow the four statutory forms (8124, 8132 to 8138). Fill them in free with our California lien waiver forms.

Related: California 20-day preliminary notice · conditional lien waivers · unconditional lien waivers · how to file a mechanics lien · lien deadline calculator

The four Texas and California waiver forms, one page each: conditional waiver and release on progress payment · unconditional waiver and release on progress payment · conditional waiver and release on final payment · unconditional waiver and release on final payment.

Read November 21, 2026. We prepare forms from the facts you enter; we do not serve, file or record documents. Not legal advice and not a substitute for the advice of an attorney.

Published November 21, 2026 · 3 min read

Lien Rights Kit
Lien waivers, notices and deadlines for subcontractors and suppliers, state by state. See pricing

Also from our guides